Discover GW Campus Development Community Notices Contact GW - Day or Night
Neighborhood Home

Overview

Historic Preservation Plan

Streetscape Plan

Community Outreach

Shared Benefits

Compliance

Overview

Regulatory Filings

Current Projects

Square 39/School of Public Health & Health Services

Square 55/Science & Engineering Hall

Square 75

Square 77

Square 102/GW Museum & The Textile Museum

Square 103/Phase I - Law Learning Center Garage

Gelman Library Renovation

Ross Hall Renovation

Virginia Science and Technology Campus

Completed Projects

Overview

Project Updates

Overview

Programmatic Partnership

Development Partnership

Project Updates

Contact Us

Square 55/"Science & Engineering Hall":
UPDATES

Square 55/"Science & Engineering Hall" Summer 2012 FACT SHEET

Daily Photos of Construction Site

For more information, mail talktogw@gwu.edu

CONSTRUCTION UPDATES in reverse chronological order

Square 55/April 26, 2013: Ongoing concrete activities for walls, columns, and slabs will continue as structure work progresses upward through the fall of 2013. This work includes setting shoring and wood formwork, setting reinforcement and in-slab utilities, pouring concrete, removing formwork, and ultimately removing the shoring. Mechanical, electrical, and plumbing workers will follow the concrete work with early rough-in activities.  Currently this work is focused on floors LL2 and LL1.  Since work during coming months will be similar in pattern, the next update will be on May 17, 2013 unless otherwise needed for additional activities that may impact the campus.

Square 55/March 29, 2013: Ongoing concrete activities for walls, columns, and slabs will continue as structure work progresses upward through the fall of 2013. This work includes setting shoring and wood formwork, setting reinforcement and in-slab utilities, pouring concrete, removing formwork, and ultimately removing the shoring. Mechanical, electrical, and plumbing workers will follow the concrete work with early rough-in activities.  Currently this work is focused on floors G1 and LL1.  Since work during coming months will be similar in pattern, these bi-weekly updates are being reduced to monthly with next update on April 26, 2013 unless otherwise needed for additional activities that may impact the campus.

Square 55/March 1, 2013: 
Excavation of footings in the north wing is complete in preparation for placing the footings. Ongoing concrete activities for walls, columns, and slabs will continue as structure work progresses upward through the fall of 2013. This work includes setting shoring and wood formwork, setting reinforcement and in-slab utilities, pouring concrete, removing formwork, and ultimately removing the shoring. Mechanical, electrical, and plumbing workers will follow the concrete work with early rough-in activities. Currently this work is focused on floors G2 and G1.  Since work during coming months will be similar in pattern, these bi-weekly updates are being reduced to monthly with next update on March 29, 2013 unless otherwise needed for additional activities that may impact the campus.

Square 55/February 15, 2013: Excavation of footings in the north wing is underway in preparation for placing the footings. Ongoing concrete activities for walls, columns, and slabs will continue as structure work progresses upward through the fall of 2013. This work includes setting shoring and wood formwork, setting reinforcement and in-slab utilities, pouring concrete, removing formwork, and ultimately removing the shoring. Mechanical, electrical, and plumbing workers will follow the concrete work with early rough-in activities. Currently this work is focused on floors G2 and G1.

Square 55/January 31, 2013: Excavation of footings in the north wing is underway in preparation for placing the footings. Ongoing concrete activities for walls, columns, and slabs will continue as structure work progresses upward through the fall of 2013. This work includes setting
shoring and wood formwork, setting reinforcement and in-slab utilities, pouring concrete, removing formwork, and ultimately removing the shoring. Mechanical, electrical, and plumbing workers will follow the concrete work with early rough-in activities. Currently this work is focused on floors
G3 and G2.

Square 55/January 18, 2013: Excavation of footings in the north wing is underway in preparation for placing the footings. Ongoing concrete activities for walls, columns, and slabs will continue as structure work progresses upward through the fall of 2013. This work includes setting shoring and wood formwork, setting reinforcement and in-slab utilities, pouring concrete, removing formwork, and ultimately removing the shoring. Mechanical, electrical, and plumbing workers will follow the concrete work with early rough-in activities. Currently this work is focused on floors G3 and G2.  Note: Per government regulations related to the President’s Inauguration, work will not occur on this or other GW construction sites on Monday, January 21, 2013. 

Square 55/January 7, 2013: Recent and upcoming work includes:  Continuation of ramp removal excavation east of Munson Hall as well as preparation for footing and slab on grad work and completion of slab on-grade work in early January. Ongoing concrete activities for walls, columns, and slabs will continue as structure work progresses upward through the fall of 2013. This work includes setting shoring and wood formwork, setting reinforcement and in-slab utilities, pouring concrete, removing formwork, and ultimately removing the shoring. Mechanical, electrical, and plumbing workers will follow the concrete work with early rough-in activities.

Square 55/December 11, 2012:  Recognizing the importance of the upcoming December 12-21 Final Exams period, the university is extending the prohibition on construction activities likely to be exceptionally noisy to 9:00am on weekdays at the sites for all of GW’s major  construction projects, including the Science and Engineering Hall site. Workers can work from 7–9:00am during this time, but the work may not include activities that are defined here – regular work may commence after 9:00 a.m.  Also, work will not occur at these sites on Saturday December 15, 2012.

Recent and current work continues throughout the site, including:  northeast section – installation of second tower crane in early December, completion of footings, begin waterproofing at shotcrete walls, being rebar at continuous wall footings; northwest section – on Level G3, building scaffolding and alumna beams, followed by installation of rebar and concrete pour; southeast section – begin pouring foundation walls and installation of under slab drainage work; southwest section – begin building scaffolding/alumna beam deck system. 

Unless otherwise needed, the next project update for this site will be posted the first week of January 2013.

Square 55/ December 5, 2012: Temporary Road Closure of 22nd Street between H & Eye Streets beginning 4:00 a.m. Friday December 7 and continuing through midnight Sunday December 9 for the purpose of removing existing excavation equipment and installation of a second tower crane.  Although a  permit has been obtained so work may occur outside the 7 a.m.-7 p.m. standard work hours (if needed), this work is not anticipated to be exceptionally noisy.  Personnel and signage will be posted in the area to assist with pedestrian and traffic control.  Adjacent sidewalks are not anticipated to be closed during this time.

Square 55/ November 30, 2012:  Recent and current work continues throughout the site, including:  northeast section - complete lower level footing and shotcrete work; northwest section - framing for first elevated deck; southeast section - slab on grade work, northeast section - preparation for slab on grade work.

Square 55/ November 15, 2012:  Recent and current work continues throughout the site, including:  northeast section - continued removal of remaining rock and soils in the area of the previous truck entry ramp and shotcrete installation along the foundation wall as well as initial footing work; northwest section - slab on grade installation; southwest
section -underslab drainage work; southeast section - column installation work, northeast section - footing excavation/construction work.

Square 55/ October 31, 2012:  Recent and current work continues throughout the site, including:  northeast section – continued removal of remaining rock and soils in the area of the previous truck entry ramp and shotcrete installation along the foundation wall as well as initial footing work; northwest section - continued pouring foundation walls and columns and begin drainage installation; southwest section –continued pouring foundation walls/columns; southeast section – continued installation of wall rebar. 

Square 55/ October 15, 2012: After the controlled blast earlier this week, blasting activities are now completed at this site. On the northeast portion of the project site, work continues to remove remaining rock and soils in the area of the previous truck entry ramp as does shotcrete installation along the foundation wall.  There are still several lifts of rock and shotcrete to get to subgrade in the northeast corner. Steel to be delivered later this week.  On the northwest portion of the site, underground plumbing inspection is complete. On the southwest portion of the site, rebar installation continues at foundation walls.  On the southeast portion of the site, column steel and footing installation is underway. 

Square 55/October 1, 2012:  One of the remaining final controlled blasts is scheduled for Wednesday October 3, 2012 at 11:00 a.m.  It will be determined after this blast if remaining blasts are necessary.   Project work on the site over next two weeks includes: Fulbright area - sump pit installation and initial underground plumbing work; H Street west - continue pouring wall footings and begin wall/column rebar installation; H Street east - continue installation of rebar in interior footings as well as interior/wall footings; rebar installation; 22nd Street north - continue removal of former vehicle ramp; Eye Street mid-block - continue rock excavation and opening interior footings.

Square 55/September 18, 2012:  Several controlled blasts are likely within the next few weeks as this phase of work concludes.  Project work on the site over next two weeks includes: Fulbright area – continued concrete work on foundations: H  Street west – continue waterproofing and installing footing rebar; H Street east – continue excavation of footings and begin interior footing rebar installation; 22nd Street north – complete removal of former vehicle ramp. 

Square 55/September 4, 2012: Several controlled blasts are likely within the next few weeks as this phase of work concludes.  Project work on the site over next two weeks includes: Fulbright area – continued concrete operations, begin waterproofing installation; Building K area – continue waterproofing and installation of footing rebar; south and east elevations – continue excavating wall footings.  

Square 55/August 20, 2012:  The first of two tower cranes was erected August 18, 2012.  Upcoming work over the next two weeks includes continued removal of rock, installation of wall footings, waterproofing installation in the Fulbright east area, rebar installation in the wall footings of Building K area, and continued concrete operations on the east elevation.

Square 55/August 10, 2012: Temporary Street closures scheduled for August 11-12/this weekend.

On Saturday, August 11, 2012 street closures will take place on the 800 block of 24th Street, NW (24th Street from H Street to New Hampshire Avenue). This is to facilitate installation of construction equipment and per approved DC permits, equipment arrival will begin as early as 5:30 a.m. and installation work will begin at 7:00 a.m. with work expected to be completed by early evening, at which time the vehicular lanes and sidewalks in this block will be re-opened. 

On Saturday, August 11, 2012 & Sunday, August 12, 2012 street closures will also occur on the 2200 block of H Street, NW (H Street between 22nd & 23rd). To facilitate installation of the tower crane for the Science & Engineering Hall project, the 2200 block of H Street will be closed to vehicular traffic except for access to parking garage from 22nd Street only (no 23rd Street access to H Street).  Staff will be on site to direct traffic accessing garage.  Per approved DC permits, equipment arrival will begin as early as 4:00 a.m. and installation work will begin at 7:00 a.m. work is expected to be completed by Sunday evening at which time the vehicular lanes and sidewalks will be re-opened. 

Square 55/August 3, 2012:  After a long period of no daily controlled blasting activities at the Science & Engineering Hall site, this activity resumed August 2, 2012. Depending on site conditions, there is a possibility of additional blasts within the next several weeks.  Tower crane footing will be installed next week with anticipated installation of the tower crane on August 11, 12.  Upcoming work over the next two weeks includes removal of rock and installation of rock bolts for concrete

Square 55/July 23, 2012: Anticipated upcoming work over the next two weeks includes continued installation of vertical bars/toe ties throughout site and proceeding of excavation on south and east elevations to next lift of rock/clay.  Controlled blasting is not likely to commence again until the southern end of the site is fully excavated and operations move northward again. The amount of blasting remaining is expected to be minimal.

Square 55/July 9, 2012: Anticipated upcoming work over the next two weeks includes completion of fourth tier tiebacks as well as continued hauling of rock, soils, and rubble and the installation of rock bolts and shotcrete in the southern and eastern edges of the site. Additionally, rock excavation and shotcrete operations along the east side of Fulbright will occur.

Controlled blasting is not likely to commence again until the southern end of the site is fully excavated and operations move northward again. The amount of blasting remaining is expected to be minimal.

Square 55/June 26, 2012: Work will not occur on Wednesday July 4 in observance of Independence Day.  Anticipated upcoming work over the next two weeks includes completion of third tier tiebacks as well as continued hauling of rock, soils, and rubble in the southern and eastern edges of the site.  The underground storage tank between Munson and JBKO is scheduled for removal in coming weeks.

Controlled blasting did not occur last week to facilitate continued removal of old ramp on the south end of the site. Blasting operations will likely be sporadic (once or twice a week) between now and mid August as mass excavation continues.

Square 55/June 18, 2012: Controlled blasting did not occur last week to facilitate continued removal of old ramp on the south end of the site. Hauling of rock, soils, and rubble continues in the southern and eastern edges of the site, as well as lagging and tie-back operations. With rock mass excavation and controlled blasting complete at the Building K area of the site, controlled blasting and rock excavation focus now shifts to the eastern side of the site and the area under the old ramp (southern half of site). Blasting operations will likely be sporadic (once or twice a week) between now and mid August as mass excavation continues.  

View from Gelman Library on June 18

Square 55/June 4, 2012: Controlled blasting did not occur last week to facilitate continued work to complete the new entrance ramp on the north side of the site (allowing trucks to exit site at the north end near Eye Street instead of the south end near H Street).  Rock excavation and earthwork focus continues at Building K footprint. Additionally, excavation and perimeter shoring efforts at the old ramp location continues.

Square 55/May 2, 2012: While it was initially anticipated when blasting began in late April that this activity would take place on most weekdays (depending on weather and soil conditions) between 10:30-11:00 a.m., site logistics necessitate increased flexibility as to the timing of when each day’s blast will occur.  As such, controlled blasting activities will now occur at either approximately 11:00 a.m. or Noon weekdays (again, depending on weather and soil conditions) on the days that blasting is required.  This change will be in effect through the duration of blasting activities which are anticipated to continue through late June or early July.

View from Gelman Library on May 21

Controlled blasting did not occur for most of last week due to efforts to complete new entrance ramp on the north side of the site (allowing trucks to exit site at the north end near Eye Street instead of the south end near H Street).  Rock excavation and earthwork focus continues at Building K footprint.

Square 55/May 14, 2012: Controlled blasting continues in the middle of the site most days, weather permitting, and is progressing toward the Building K footprint. Adjustments continue to be made to original approximate 10:30 a.m.-11:00 a.m. timeframe window for blast times on weekdays. Recent foundation work includes continued installation of vertical bars and toe ties along 22nd Street and Fulbright North.  Earthwork includes continued work at Building K footprint and Fulbright east, continued rock excavation at Building K footprint and Munson south, and continued development of new entrance ramp on the north side of site.

View from Gelman Library on May 14

Square 55/May 4, 2012: Controlled blasting continues in the middle of the site most days, weather permitting, and is progressing toward the Building K footprint. Original approximate window of 10:30 a.m.-11:00 a.m. may be increased by one hour so blasting may occur between 9:30 a.m.-11:00 a.m. Recent foundation work included installation of vertical bars and toe ties along 22nd Street and Fulbright North.  Earthwork includes continued work at Building K footprint and Munson south and development of new entrance ramp on the north side of site.

Square 55/April 27, 2012: The first controlled blasting in the middle of the site occurred on April 26 at apx. 10:50 a.m. Additional blastings will continue each weekday for 4-5 months between 10:30 a.m. to apx. 11:00 a.m. depending on weather and soil conditions.  Recent foundation work included installation of vertical bars and toe ties an Munson Hall (which will continue at Fulbright north). Earthwork includes continued work on new entrance ramp on the north side of site and continued excavation/removal of rubble in the middle or project site and along 22nd Street.

Close-up of Controlled Blasting Location on Square 55

Square 55/April, 2012:  Excavation has progressed to the point that the contractor for this project will begin controlled blasting activities on the project as soon as April. These activities are highly monitored to ensure they are within regulated limits, do not adversely affect any adjacent structures, and have minimal impact on day-to-day routine of those living an working in close proximity to the site (the same as experienced in 2008 during the several months of controlled blasting at the Square 54 for The Avenue). When blasting begins, it will occur on most, but not all, weekdays typically between 10:30-11:00 a.m. For many, the most noticeable part of this activity will be the series of air horns that sound to notify the worksite and the public of the activity at 15 minutes, five minutes, and one minute prior to the blast, and immediately following the blast to indicate "all clear." The blasting activity itself will result in limited sound and vibration impacts that have been compared to that of a door slamming or a large truck passing and that last, at most, a few seconds (this will vary depending on a number of factors, including weather and site location). Since this activity agitates soil, occupants of buildings immediately adjacent the site are asked to keep windows closed during the blasting period (residents will not need to evacuate building during this adjacent to the site will be closed temporarily in the few minutes before and during each blasting event and adjacent streets will be temporarily closed for a few minutes during the blasting events (at the direction of D.C. Metropolitan Police and with exceptions for emergency vehicles). Blasting materials will not be stored on site.

View from Gelman Library

Square 55/April 13, 2012:  While excavation efforts have yet to discover rock that requires controlled blasting for removal, it appears this may occur within the next several weeks.  This sort of timing fluctuation is typical when working with a large project site that has varying soil conditions and will not impact the project's scheduled completion in late 2014.  Related to this, there will be a delivery this Saturday of the mats used to cover the ground in the construction site on and near the blasting activities.

Recent foundation work included completion of tieback drilling on the north side of Fulbright as well as continued installation of lagging on 22nd Street and south side of Munson Hall, and third tier cross lots. Earthwork includes continued work on new entrance ramp on the north side of site and continued excavation/removal of rubble in the middle or project site and along 22nd Street.

Square 55/April 6, 2012:  Foundation work included continued installation of lagging on 22nd Street, tiebacks on north side of Fulbright Hall and south side of Munson Hall, and third tier cross lots.  Earthwork includes completion of ramp relocation to run along H Street as well as continued excavation and removal of rubble in the middle or project site and along 22nd Street. Controlled blasting activities are now anticipated to begin in mid to late April.

Square 55/March 23, 2012:  Foundation work included continued installation of lagging at H Streets, tiebacks at east side of Fulbright and southwest corner of site, and third tier cross lots.  Earthwork includes continued excavation and demolition of remaining below grade garage structure, as well as hauling of rubble and steel, inlcluding use of hoe-ram in the first layer of rock in the cross lot area. Controlled blasting activities are now anticipated to begin in late March or early April.

View from Gelman Library

Square 55/March 9, 2012:  Foundation work included continued installation of lagging at 22nd and H Streets, tiebacks south of Munson Hall near 22nd Street, and third tier cross lots.  Earthwork includes continued excavation and demolition of remaining below grade garage structure, as well as hauling of rubble and steel.  Demobilization of major equipment (crane) will occur in next week and should have little to no impacts on vehicular or pedestrian access. 

Square 55/ March 2, 2012:  Over the next two weeks the following activities will be occurring onsite: the third tier of crosslot bracing between JBKO and Munson Halls will be installed; tie-backs east of Fulbright Hall and along H Street will be installed; angled steel supports will be installed east of Munson Hall;  the large mobile crane will be removed from the site on Saturday, March 10th which will require a partial road closure on H Street between 22nd and 23rd Streets - which may require brief restrictions of vehicular traffic lanes which will be facilitated by construction personnel.   Additionally, excavation and below grade demolition will occur east of Fulbright Hall and along H Street,  22nd Street, and both south and east of Munson Hall.  Major deliveries will include steel deliveries for the crosslot bracing and the angled steel for the north end of the site which should not cause any road closures.

View of site from Gelman Library

Square 55/February 26, 2012: Demolition of below grade structure and concrete/rubble removal to the second tier tieback elevation continues east of Munson Hall and along 23rd Street. Excavating, lagging, and drilling ties continues in the second tier along 22nd Street.   Tieback installation occurs at various locations throughout the site. Installation continues on third tier supports for cross lot bracing as does installation of vertical bars at the base of piles in the cross lot area. Clark Construction completed installation last Saturday of its trailer for administrative uses on the H Street on side of the project.

Square 55 / February 17, 2012: This Saturday (February 18), Clark Construction will install a trailer for administrative uses on the H Street on side of the project which may require brief restrictions of vehicular traffic lanes which will be facilitated by construction personnel. Work will occur on Monday February 20 (President's Day Holiday) but will adhere to the adjusted work hours used during final exams periods: limited construction allowed at 7:00 a.m. start time - no exceptionally noisy work before 9 a.m..  Excavation continues at the cross lot area to the elevation of the third tier of cross lots.  Demolition of below grade structure and concrete/rubble removal to the second tier tieback elevation continues east of Munson Hall and along 22nd Street.  A second cut will occur near the east side of Fulbright Hall, working toward the project's H Street entrance ramp.  Tieback installation occurs at various locations throughout the site. Installation continues on third tier supports for cross lot bracing

Close-up of Fullbright Hall

Square 55/February 13, 2012: Ongoing excavation efforts include removal of soils (east of Fulbright and Munson Halls) and below grade rubble and steel. Removal of soils under the cross-lot bracing will be underway as well. Below grade demolition of 1971 and 1999 portions of UPG continues, especially east of Munson. Sheeting and shoring efforts include installation of tie-back systems (along H Street/south of Munson), and wood lagging at various locations of the site as they are excavated.  Some work during the next week may produce intermittent periods of increased vibrations/noise near Munson as removal continues of below-grade west wall of the 1999 portion of UPG.  Also, PEPCO has planned to replace transformers at the northeast corner of the site -- however, the exact date and time has not yet been determined. This work should occur inside the construction fence and is unrelated to the Science and Engineering Hall project.

View of site from Gelman Library

Square 55/February 3, 2012: Some work during the next week may produce intermittent periods of increased vibrations/noise near Munson Hall and Fulbright as removal continues of below-grade portion of the west wall of the 1971 portion of the University Parking Garage.  Replacement of excavation equipment will take place along 22nd Street on March 6 -- traffic will remain open and be diverted around this loading activity. Work will begin soon by PEPCO to replace transformers at the northeast corner of the site. Although this work will likely occur inside the construction fence, it not related to the Science & Engineering Hall project.  More details (including days/times) will be shared when they are made available by PEPCO. Ongoing excavation efforts include removal of soils (east of Fulbright Hall and south of Munson) and below grade rubble and steel. Below grade demolition of 1971 and 1999 garage continues. Sheeting and shoring efforts include installation of tie-back systems (along H-street and South of Munson), and wood lagging at various locations of the site are excavated. Structural steel will be installed on the soldier piles along Eye Street as well.

Close-up view of the rear of JBKO and Munson

Square 55/January 27, 2012:  Some work during the next week may produce intermittent periods of increased vibrations/noise near Munson and Fulbright Halls as removal continues of below-grade portion of the west wall of the 1971 portion of UPG. Ongoing excavation efforts include removal of soils (east of Fulbright Hall and along 22nd Street) and below grade rubble and steel. Below grade demolition of 1971 and 1999 garage continues. Sheeting and shoring efforts include installation of tie-back systems (near Fulbright Hall), cross-lot bracing, and wood lagging at various locations of the site are excavated.

Square 55/January 19, 2012: Drilling of piles on site is complete. Installation of trailer platform on the project's south side continues.  Work has begun on the next tier of cross lot support beams on the project's west side.  Lagging and tiebacks continue at various site locations.  Excavation of soil and existing below grade rubble/steel continues in all areas of the site except where the cross lot support.

Square 55/January 12, 2012:  Security lighting has been installed at the project site and this lighting will remain on overnight to provide security for the project site.  Please contact talktogw@gwu.edu if this lighting impacts your room when blinds are closed.  Similar lighting may also be required at the Law Learning Garage site later this semester.

View of site from Gelman Library during the evening.

Beginning Saturday January 14, 2012, the prohibition on construction activities likely to be exceptionally noisy to 8:00am on weekdays and 9:00am on Saturdays will resume (to clarify, workers can work beginning at 7am but it should not include activities defined as "exceptionally noisy": surface scraping and asphalt/concrete demolition; filling of dump
trucks/dumpsters with large rubble or scrap metal (soil is permitted); jack hammering; driving of piles; repeated/continuous honking/idling in vicinity of residence halls, and; loud/boisterous outdoor conversations within close proximity to residence halls.

Although the university will be closed on Monday, January 16 in observance of the Martin Luther King, Jr. Holiday, work will take place at the project site in acco, rdance with hours noted above.

Current work includes: drilling piles complete around perimeter of site; lagging and tiebacks continue at various site locations; excavation of soil continues below cross lot area, east of Fulbright Hall and east of Munson Hall, and; demolition of remaining existing below grade structure continues, including hauling of rubble and steel.

Square 55/Dec 21, 2012: After GW's final exam period concludes on December 21, the university will lift its prohibition on early morning exceptionally noisy activities (7-8am weekdays, 7-9am Saturdays) so all work activities may begin starting at 7am.  Beginning Saturday January 15, 2012, the prohibition on construction activities likely to be exceptionally noisy to 8:00am on weekdays and 9:00am on Saturdays will resume (to clarify, workers can work beginning at 7am but it should not include activities defined as “exceptionally noisy”: surface scraping and asphalt/concrete demolition; filling of dump trucks/dumpsters with large rubble or scrap metal (soil is permitted); jack hammering; driving of piles; repeated/continuous honking/idling in vicinity of residence halls, and; loud/boisterous outdoor conversations within close proximity to residence halls.

In observance of the holidays work will not occur on Monday December 26 or Monday January 2.

Square 55/December 19 , 2011: This week the following activities are scheduled to occur:

  • Drilling of steel soldier piles along 22nd Street.


    View of site from Gelman Library December 16, 2011

  • Installation wood lagging boards between the steel soldier piles along 23rd Street
  • and along the Southern side of JBKO/Munson.  
  • Mass excavation and foundation debris removal will occur from 23rd Street eastward along the southern edge of JBKO and Munson.
  • Mass excavation east of Fulbright will begin.
  • The construction entrance ramps will be relocated.  
  • Surveying of foundation and building monitoring will be ongoing.

Square 55/December 12, 2011: This week the following activities are scheduled to occur:

  • Perimeter lights will be installed for evening work that occurs after dark.
  • Drilling of steel soldier piles along 22nd Street.
  • Installation wood lagging boards between the steel soldier piles along 23rd Street and along the southern side of JBKO/Munson.
  • Concrete bracket pile installation under JBKO building footings will be completed in the next week.
  • Mass excavation and foundation debris removal will occur from 23rd Street eastward along the southern edge of JBKO and Munson.
  • Surveying of foundation and building monitoring will be ongoing.


Closer view of site from Gelman Library December 12, 2011

Recognizing the importance of the upcoming Final Exam period, we are extending the prohibition on construction activities likely to be exceptionally noisy to 9:00am on weekdays (remember, workers can work from 7–9:00am during this time, but the work may not include activities that are defined below – also, regular work may commence after 9:00am). Additionally, work will not occur on Saturday, December 17, 2011.

To help clarify, “exceptionally noisy” activities are defined as: surface scraping and asphalt/concrete demolition; filling of dump trucks/dumpsters with large rubble or scrap metal (soil is permitted); jack hammering; driving of piles; repeated/continuous honking/idling in vicinity of residence halls, and; loud/boisterous outdoor conversations within close
proximity to residence halls.

If you have questions regarding construction activities that have been prohibited during early hours due to their likelihood of resulting in exceptionally noisy conditions, please email either talktogw@gwu.edu or campaign@gwu.edu or tweet @GWDOSHelps.  We also urge you to use any of these contacts if there has been a violation of these prohibitions (please share as much information as possible, especially time of day/type of
noise) so we can immediately follow up with the construction team.

Square 55/December 2, 2011: Drilling activity on the southeast side of the project continues. All drilling is anticipated to finish by end of the year. Drilling along the east side of Munson should wrap up in coming weeks. Grout tube installation at south side of Munson is ongoing. Excavation from 23rd Street and moving eastward along the south side of JBKO and Munson is underway. Installation of lagging boards along the west and northern edges of the excavation will follow the excavation work.  Bracket pile installation at east side of Fulbright to complete early this week. Underpinning at the top of drilled bracket piles will commence at Fulbright this week. Once these are complete, underpinning at Munson will commence. Underpinning pits at JBKO are complete. Work on the existing east façade of Munson will continue including installation of additional drilled anchors on the exterior.


View of site from Gelman Library November 20, 2011

Square 55/November 18, 2011: Drilling activity on the west side of the project near Fulbright Hall continues as well as at other areas around the site. Work continues on underpinning pits near JBKO with expected completion this week. Pile installation continues in vicinity of Fulbright and Munson Halls. Soldier pile driling continues at southwest corner of site. Grout tube installation near Fulbright is complete. Excavation activities will commence working from west to east just south of JBKO and Munson. Additionally, work on the existing east façade of Munson will commence including installation of drilled anchors on the exterior and the installation of a block wall on the interior.

Square55/November 11, 2011: Processing/removal of demolished material from below-grade portion of 1971 garage and 1999 garage continues as part of the sheeting, shoring and excavation process. Drilling activity on the west side of the project near Fulbright Hall continues as well as at other areas around the site. Work continues on underpinning pits near JBKO and Munson. Pile installation continues in vicinity of Fulbright and Munson Halls. Soldier pile drilling at 23rd Street is complete and progressing to southwest corner of site.

Square 55/November 4, 2011: As part of the construction of the Science & Engineering Hall, PEPCO will be pulling wire the week of November 7 at night on 22nd Street between H and Eye Streets - crossing H street to the corner of Gelman library. The work was scheduled at night by the Pepco due to the level of traffic from pedestrians and cars in the area. The work is anticipated to start at midnight each night and will last thru Thursday night and should not be noisy. Please contact either talktogw@gwu.edu or campaign@gwu.edu if you have additional comments/questions. Also, additional light stands will be installed around the site and be used in the late afternoon hours beginning Monday November 7 due to the time change. These lights will be used only during permitted work hours (Monday to Saturday, 7am-7pm). Please contact talktogw@gwu.edu or campaign@gwu.edu if these lights create a disturbance.


View of site from Gekman Library November 4, 2011

Processing/removal of demolished material from below-grade portion of 1971 garage and 1999 garage continues as part of the sheeting, shoring and excavation process. Drilling activity on the west side of the project near Fulbright Hall continues as well as at other areas around the site. Work continues on underpinning pits near JBKO and Munson. Pile installation continues in vicinity of Fulbright and Munson Halls.

Square 55/October 28, 2011: Processing/removal of demolished material from
below-grade portion of 1971 garage and 1999 garage continues as part of
the sheeting, shoring and excavation process. Drilling activity on the
west side of the project near Fulbright Hall continues as well as at other areas around the site. Work continues on underpinning pits near JBKO and Munson. Pile installation to begin in vicinity of Fulbright and Munson Halls.


The construction site on October 20, 2011, the day of the ground breaking ceremony
.

Square 55/October 21, 2011: The official groundbreaking ceremony for this project was held last night and attended by hundreds of students, faculty, staff, alumni, neighbors, and friends of the university. Processing/removal of demolished material from below-grade portion of 1971 garage and 1999 garage continues as part of the sheeting, shoring and excavation process. Drilling activity on the west side of the project near Fulbright Hall continues as well as at other areas around the site. Work continues on underpinning pits near JBKO and Munson Hall. Pile layout has begun at various site locations.

Square 55/October 14, 2011: Processing and removal of the demolished material continues. Removal of below-grade portion of 1971 garage and 1999 garage continues as part of the sheeting, shoring and excavation process. Drilling activity on the west side of the project near Fulbright Hall continues as well as at other areas around the site. Work on the JBKO and Fulbright walls is complete. First dewateringpit has been installed on north side of Fulbright and work continues on underpinning pits near JBKO.


Construction site October 18, 2011

Square 55/October 6, 2011: Processing and removal of the demolished material will continue for several weeks. Removal continues of below-grade portions of the former parking garages as part of the sheeting, shoring and excavation process. Drilling activity on the west side of the project near Fulbright Hall continues as well as at other areas around the site. Work is nearing completion on the south wall of JBKO residence hall.

Square 55/September 29, 2011: Above-grade demolition of the 1971 and 1989 garages is complete: processing and removal of the demolished material will continue for several weeks. The large orange high reach excavator was demobilized. Below grade portions of the both parking garages will be removed as part of the sheeting, shoring and excavation process. This process has started with drilling activity on the west side of the project near Fulbright Hall. In addition, work will take place for next one-two weeks to drill anchor placements on the south wall of JBKO residence hall.

University Parking Garage demolition
September 2011
View from I and 22nd Streets

Square 55/September 22, 2011: Demolition of the 1971 garage continues with removal of above grade structure to be finished early next week and then below grade demolition on both the 1971 and 1989 structures to continue for several weeks, leading into excavation which will be ongoing for rest of the academic year. The drill rig for in preparation for sheeting and shoring continues work on the west side of the project near Fulbright Hall.

Square 55/September 15, 2011: Demolition of the 1971 garage continues and is anticipated to reach grade level during the next week.  Upon completion of above grade demolition the "high reach" demolition crane will be dismantled. Demolition work continues on below grade levels of the 1989 garage, as well as underpinning and prepartion for upcoming excavation and sheeting/shoring activities."

Square 55/September 8, 2011: Demolition of the 1971 garage continues over the next several weeks until reaching grade level.  Work continues on below grade levels of the 1989 garage. Underpinning work is underway on JBKO as well as some patching of exterior walls.  Following demolition, excavation, sheeting, and shoring to grade will begin.  

Square 55/August 29, 2011: Demolition work on the 1999 parking garage has progressed to ground level.  Demolition work on the 1971 parking garage continues.

University Parking Garage demolition
August 2011
View from I and 22nd Streets

Square 55/August 15, 2011: The temporary trailer to house on-site construction managers/workers was installed in late July. Demolition of Building K on 23rd Street, NW is complete. Demolition work on the 1999 parking garage has progressed down six levels, witha floor being removed approximately every four days. Demolition work on the 1971 parking garage began last week and will proceed from the structure's western portion to the east. 

 

 

 

 

 